Test Your Code Knowledge – Volume 3.6

TOPIC: Weld Buildup of Wasted Area

    ————–

Question: When performing weld metal buildup of wasted areas of pressure retaining items, is the wall thickness required to be restored to the thickness listed on the Manufacturers Data Report?

No. The thickness after build-up shall be the original thickness of the pressure retaining item minus the corrosion allowance.